Jerusalem Light Rail depot

Strengthening the foundation of a retaining wall at the Jerusalem Light Rail depot, 2019: careful trimming of unstable rock, 77 galvanised rock bolts 10 m long, a sprayed concrete wall and stone cladding.

Location
Jerusalem Light Rail depot, Jerusalem
Years
2019
Status
Completed

Quantities executed

  • 77 rock boltsGalvanised rock bolts, 10 m
  • approx.215 m³Sprayed concrete retaining wall
  • approx.320 m²Stone wall cladding
  • 50 m³Careful trimming of unstable rock

The challenge

The task: strengthen the foundation of an existing retaining wall at the Jerusalem Light Rail depot. In other words, work beneath a wall that was already standing, rather than build a new one from scratch. There was unstable rock on site, and we trimmed it back carefully. We strengthened the wall with rock bolts and a sprayed concrete wall, and clad it in sawn and dressed stone. The new sprayed wall is up to 5 m high. We worked as a subcontractor to the main contractor on site. The work had four components: careful rock trimming, rock bolts, a sprayed concrete wall reinforced with 6.4 tonnes of steel mesh, and stone cladding.

What we did

  • Careful trimming of unstable rock50 m³
  • Drilling and grouting of 77 galvanised rock bolts, 25 mm diameter, each 10 m long770 m
  • B30 sprayed concrete retaining wall, up to 5 m high216 m³
  • Steel reinforcing mesh6.4 t
  • Sawn and dressed stone cladding on the wall316 m²

What sets it apart

All 77 bolts were drilled and grouted in about five weeks, between 17 September and 22 October 2019, and logged in a grouting record. 77 bolts at 10 m each add up to 770 m of drilling in rock.