Blue Line – northern portal, Golda Meir Boulevard
Enabling works at the northern portal of the Blue Line tunnel in Jerusalem, for Moriah: carriageway removal, excavation, approx. 12 km of electrical and communications ducting, sewage, drainage and paving, to prepare the site for the tunnel excavation.
- Client
- Moriah – Jerusalem Development Corporation
- Location
- Golda Meir Boulevard, Jerusalem
- Years
- 2021–2023
- Status
- Completed
Services
Quantities executed
- approx.12 kmElectrical and communications ducting
- approx.7,850 m²Carriageway removal
- approx.2,100 m³Excavation
- approx.1,600 m³Trial pits to locate utilities
- approx.1,200 m³CLSM concrete
- approx.500 mAcoustic panel wall
The challenge
The northern portal of the Blue Line tunnel sits on the Golda Meir Boulevard corridor in Jerusalem. To clear the site for the tunnel excavation, we removed existing carriageways, excavated and built underground infrastructure for the rail corridor. Existing utilities run under the road, so we dug approx. 1,600 m³ of trial pits to locate them. The work ran from August 2021 to January 2023.
What we did
- Carriageway removal, up to 60 cm deep7,859 m²
- Excavation and removal of soil2,118 m³; trial pits to locate utilities — 1,610 m³
- Electrical and communications ducting (PVC 8″ and 4″, HDPE, Bezeq telecom, corrugated)12,113 m
- Sewer lines404 m; reinforced concrete drainage pipes — 315 m
- CLSM concrete1,185 m³
- Type-A sub-base1,997 m³; dense asphalt concrete (25 mm), surface course — 10,392 m²
- Kerbs1,430 m
- Acoustic panel wall, 2.5 m high300 m, plus 216 m on an existing wall
- Demolition of existing retaining walls195 m³
What sets it apart
Every quantity on this page is the quantity Moriah approved in the final account. In 2024 Uri Kashriel, on behalf of Moriah, completed a reference form for the work at the northern portal.